§ 332. Actions for Which Board Is Retained.

23 CA ADC § 332BARCLAYS OFFICIAL CALIFORNIA CODE OF REGULATIONS

Barclays Official California Code of Regulations Currentness
Title 23. Waters
Division 2. Department of Water Resources
Chapter 1. Dams and Reservoirs
Article 5. Dams Owned by the Department of Water Resources (Refs & Annos)
23 CCR § 332
§ 332. Actions for Which Board Is Retained.
(a) The department shall retain a consulting board:
(1) To review the adequacy of the design of a dam and reservoir the department proposes to construct, or
(2) To review the safety of the completed construction and the terms and conditions to be included in a certificate of approval for any dam owned by the department as issued, renewed or modified, no later than six months following any such action.
(b) Where a board is retained to review the adequacy of the design of a dam and reservoir, it shall report its findings to the Director prior to the approval of an application to construct or enlarge the dam.
Note: Authority cited: Section 6078, Water Code. Reference: Section 6056, Water Code.
HISTORY
1. Renumbering and amendment of former Section 332 to Section 322 and renumbering and amendment of former Section 342 to Section 332 filed 8-4-83; effective thirtieth day thereafter (Register 83, No. 32). For prior history, see Register 77, No. 33.
This database is current through 6/17/22 Register 2022, No. 24
23 CCR § 332, 23 CA ADC § 332