007.40.2-VII. Notification for Lead -- Based Paint Abatements Performed on Target Housing or Ch...
AR ADC 007.40.2-VIIArkansas Administrative CodeEffective: September 27, 2021
Effective: September 27, 2021
Ark. Admin. Code 007.40.2-VII
Formerly cited as AR ADC 007.04.11-VII
007.40.2-VII. Notification for Lead -- Based Paint Abatements Performed on Target Housing or Child-Occupied Facilities
(1) For all projects involving lead -- based paint abatement activities on target housing or child-occupied facilities, the building owner and/or the licensed lead -- based paint contractor or consultant shall submit written notification on the notification form provided by the Department for each target house intended to be occupied as a single-family dwelling and each child-occupied facility and all applicable fees.
All written notifications shall be submitted on a form provided by the Department and shall include the following:
(9) If an inspection, risk assessment, or lead-hazard screen has been performed, the date performed, the certificate number, discipline, and name of the individual who performed the lead -- based paint activity, and the license number and name of the firm for whom the individual performed the lead -- based paint activity;
The Department may waive the 10-day notification period if an emergency, as defined by this rule, exists, and the building owner and/or the lead -- based paint contractor or lead -- based paint consultant complies with the following:
(1) The building owner and/or the lead -- based paint consultant or lead -- based paint contractor must notify the Department by telephone to request an emergency waiver, stating the nature of the emergency, as soon as the emergency is detected. If such emergency occurs at night, on holidays, or on weekends, the necessary corrective measures may be taken at that time and the telephone call shall be made on the first workday following the detection of the emergency.
(1) The Department shall review all notifications for accuracy and completeness and may return a deficient notification to the building owner and/or the lead -- based paint contractor or consultant submitting the notification along with a Notice of Deficiency. The NOI shall be corrected and resubmitted by the building owner and/or contractor or consultant and shall be subject to a new notification period.
(2) A building owner and/or consultant or contractor who has already submitted a notification shall notify the Department in writing no later than three working days prior to the effective date of the Notice of Intent of any changes not listed in ยง VII(e)(1). Since an additional fee is not required to accompany these revisions, these revised notifications may be sent by facsimile or by mail.
Credits
Adopted Dec. 11, 2020; Sept. 27, 2021.
Current with amendments received through February 15, 2024. Some sections may be more current, see credit for details.
Ark. Admin. Code 007.40.2-VII, AR ADC 007.40.2-VII