006.27.3-R4:19-11-244. Stay of Procurements During Protest.
AR ADC 006.27.3-R4:19-11-244Arkansas Administrative Code
Ark. Admin. Code 006.27.3-R4:19-11-244
006.27.3-R4:19-11-244. Stay of Procurements During Protest.
When a protest has been timely submitted, no execution of the contract shall be made until the protest has been settled or determined by the State Procurement Director or relevant procurement agency head, unless the State Procurement Director or relevant procurement agency head makes a written determination, after consulting with the head of the using agency or the head of the procurement agency, that the execution of the contract without delay is necessary to protect substantial interests of the State.
Credits
Adopted Jan. 1, 1999.
Current with amendments received through February 15, 2024. Some sections may be more current, see credit for details.
Ark. Admin. Code 006.27.3-R4:19-11-244, AR ADC 006.27.3-R4:19-11-244