226.00.1-12. The Sixty (60) Day Application Process for Certificate of Need Reviews
AR ADC 226.00.1-12Arkansas Administrative CodeEffective: September 9, 2022
Effective: September 9, 2022
Ark. Admin. Code 226.00.1-12
226.00.1-12. The Sixty (60) Day Application Process for Certificate of Need Reviews
The following is a summary of the process for submitting and the progression of an application for a Certificate of Need. Each step in the process must be completed prior to issuing or denying a Certificate of Need.
c. Determination of Completeness -- The SEARSWMB will determine the completeness of an application, and within two (2) weeks of receipt of an application, notify the applicant of any additional information necessary for completion of the application. If no requests for additional information are made by the SEARSWMB within two (2) weeks, the application will be deemed to be complete and affected persons will be notified of the beginning of review. (Refer to Rule 9, Paragraphs a and d)
d. Beginning of Review -- The initiation of the sixty (60) day review period begins on the date of notification by the SEARSWMB, by letter, to the applicant of the completeness of the application and the beginning of the review or the date that the public notice appears in the newspapers, whichever is later. (Refer to Rule 9, Paragraph a)
Credits
Adopted Sept. 9, 2022.
Current with amendments received through February 15, 2024. Some sections may be more current, see credit for details.
Ark. Admin. Code 226.00.1-12, AR ADC 226.00.1-12
End of Document |